A Commencement Notice is required to give notice to Building Control Authorities of the erection of such buildings, or classes of buildings, or the carrying out of such works, or classes of works, as may be specified in the regulations.
Link to Building Control Management System
The National Building Control Office (NBCO) has a Youtube Channel that gives users of BCMS guidance videos on how to upload Commencment Notices, 7 day notices, Disability Access Certificates, Fire Safety Certificates
Click on the link for the NBCO YouTube Channel https://www.youtube.com/channel/UCCCjy80kctZ34oujewzgKEA/featured
In accordance with the Building Control (Amendment) Regulations S.I. 9 of 2014, you are obliged to submit a Commencement Notice prior to commencement of a development and it must be received by the Building Control Authority not less than 14 days and not more than 28 days before you wish to commence.
You need to submit a Commencement Notice if you are:
Please note that in accordance with the Building Control (Amendment) Regulations (S.I.9) of 2014 from March 1st 2014 new procedures in relation to the submission of Commencement Notices and 7 Day Notices come into effect.
Forms must be submitted electronically via the Building Control Management System website, as paper copies are no longer accepted. In short the new requirements will apply to:
Additional documentation will be required to be submitted with the completed Commencement Notice for;
Check List to accompany a Commencement Notice:
Any Commencement Notice submitted after the 1st March 2014, which comes within the scope of Building Control (Amendment) Regulations (S.I. 9) of 2014 must fill out an online assessment of the proposed approach to compliance with the Building Regulations and be accompanied by the following:
With regard to the above, please ensure the following is adhered to:
The Commencement notice and accompanying documentation must all be filed electronically via the online Building Control Management System (BCMS).
There are guidance videos on how to use BCMS ...... https://www.youtube.com/channel/UCCCjy80kctZ34oujewzgKEA/featured
7 Day Notice
A 7 Day notice is a fast track notification of commencement, prior to the granting of a Fire Safety Certificate.
The standard fee for a 7 Day notice is €250 or €5.80 per square metre of floor, whichever is the greater. This is double the amount for a standard Fire Safety Certificate application.
The 7 Day notice must be accompanied by a valid Fire Safety Certificate application and a Statutory Declaration form in respect of the work proposed, but only the fee for the 7 Day notice applies
The name of the applicant on the Statutory Declaration form must match that of the applicant on the 7 Day Notice form along with the description of works on the Statutory Declaration which must match the description provided on the 7 Day Notice application form. The Statutory Declaration must be signed, addressed, dated and stamped by a Commissioner of Oaths